Timeline
The details below provide information regarding the status of construction activities and corresponding timelines.
Clearwater River Valley Construction
- Successfully completed the Woodland Pipeline Project horizontal directional drill (HDD) and pipeline installation under the Clearwater River and through the Clearwater River valley, jointly constructed with the Norealis Pipeline Project.
Pipeline
- As of late November/early December 2011 pipeline construction crews began mobilizing in the field to begin right-of-way preparations and grade work.
- Pipeline construction commenced in early January 2012 and is expected to be completed in March 2012.
Cheecham Terminal
- The two tanks were assembled over the summer 2011; crews are currently constructing the tank roofs and interconnecting pipe.
- The tanks will be hydro tested in March/April 2012 and the tank exteriors will be painted following the hydro test.
- The tanks are expected to be completed by September 2012.
Woodland Pump Station
- Construction of the Pump Station is ongoing and will be completed in June 2012.
The expected project in-service date is September 2012.