Project OverviewThe Hardisty Contract Tankage project includes 19 new tanks located adjacent to Enbridge’s existing mainline system terminal at Hardisty, Alberta. The tanks are typical of those already used by Enbridge Pipelines Inc. and range in size from 250,000 to 530,000 barrels for a total capacity of 7.5 million barrels (bbl). While tanks in the existing Hardisty Terminal are used as part of the mainline operation, these new tanks will house products from specific companies for longer periods of time. Hardisty Contract Tankage Project components include:
The facility has an initial capacity of 7.5 million barrels in total (approximate) and includes room for future expansion, which may include additional tanks and truck unloading facilities. Construction UpdateConstruction at the Hardisty Terminal began in early 2007. Phase 1:
Phase 2A:
Phase 2B:
Painting of completed tanks began in May 2009 and will continue until July 2010. |
||
|