Whitetail Peaking Station

Return to project


Timeline

Enbridge's schedule for this Project is as follows:

  • Project received the AUC and AESRD permits in late 2014 and early 2015, respectively;
  • ATCO and AESO have submitted their applications to the AUC for the electrical interconnect in late 2014 and early 2015;
  • Subject to obtaining all necessary approvals, begin construction in 2018; and
  • Station in full operation by Q4 2020.

We will update this timeline as the Project progresses.