Cameron Extension Project

The Cameron Extension Project will provide firm natural gas transportation supply to Venture Global LNG's Calcasieu Pass LNG export terminal in southwestern Louisiana.

Once in-service, the Cameron Extension Project will provide 750,000 dekatherms per day (Dth/d) of firm natural gas transportation supply to the Calcasieu Pass LNG facility in Cameron Parish. The project is anticipated to be placed in-service the second half of 2021.

Project facilities will include a new 30,000 horsepower compressor station, new metering and regulating stations, approximately 0.2 miles of 30-inch diameter interconnecting piping, and installation and modification of various equipment and facilities at existing sites along Texas Eastern’s Line 41 in Beauregard, Cameron, and Jefferson Davis Parishes, Louisiana.

The project will be constructed using proven and safe techniques and is designed to minimize potential impacts to landowners, the environment and communities, as project facilities will be within, along or adjacent to existing utility and transportation corridors.

Texas Eastern is an indirect, wholly owned subsidiary of Enbridge Inc.

Loading
Processing
There are no assets that meet your criteria.
Please modify the filters.

Project overview:

  • Type: Natural gas pipeline
  • Status: Under construction
  • Peak day capacity: 750,000 dekatherms per day (Dth/d)
  • Expected to transport: Natural gas
  • In-service target date: 2021
  • Ownership: Texas Eastern Transmission, LP
  • FERC docket number: Docket No. CP19-512-000

Project Information:

Project Timeline

  • Filed FERC application Sept. 26, 2019
  • FERC certificate received June 18, 2020
  • Construction commenced Jan. 4, 2021
  • Targeting full in-service in 2021