Unplanned outage on T-South system

February 01, 2023

INFORMATION UPDATE: Thursday, Feb. 2, 9:20 a.m. PT

Crews were dispatched to site and completed assessments to ensure the ongoing safety and integrity of the pipeline. Our 36-inch pipeline was returned to full service on Feb. 1, 2023 and there are no further impacts to gas supply along our T-South system.

Wednesday, Feb. 1, 2023, 7:05 a.m. PST

Yesterday, Enbridge undertook an unplanned outage on our T-South system.  Safety of the public, employees and community is always our top priority as we operate and maintain our assets.

As a precaution, a segment of our 36 inch pipeline near Chilliwack, BC was isolated to facilitate required assessments while our 30 inch pipeline continued to operate. Those assessments have been completed and we are currently repressuring the 36 inch pipeline to return to full service.

During this time we are working with industry partners to manage the potential impact to our customers and the public.