Line 26 Optimization

Return to project

Preliminary project timeline

First half of 2026

  • In-person discussions and public engagement events begin with landowners, communities, Tribal Nations, First Nations and Métis governments, as well as other interested stakeholders
  • Environmental and geotechnical field studies begin

Mid-2026

  • Enbridge makes a decision whether to proceed with the project

Second half of 2026

  • Required regulatory applications begin to be filed (pending a decision to proceed with the project)
  • Project discussions with landowners, residents, local government, communities, and Indigenous groups continue

2027 and 2028

  • Pipeline construction, and construction at Enbridge facilities, expected to begin
  • Targeted project in-service date late 2028