Line 26 Optimization
Return to projectPreliminary project timeline
First half of 2026
- In-person discussions and public engagement events begin with landowners, communities, Tribal Nations, First Nations and Métis governments, as well as other interested stakeholders
- Environmental and geotechnical field studies begin
Mid-2026
- Enbridge makes a decision whether to proceed with the project
Second half of 2026
- Required regulatory applications begin to be filed (pending a decision to proceed with the project)
- Project discussions with landowners, residents, local government, communities, and Indigenous groups continue
2027 and 2028
- Pipeline construction, and construction at Enbridge facilities, expected to begin
- Targeted project in-service date late 2028