Mainline Optimization
Return to projectProgram timelines
Mainline Optimization Phase 1
2024
- Early project planning and development
First half of 2025
- Ongoing project design and development
- Public engagement begins with government, Tribal Nations, First Nations and Metis governments, as well as other interested stakeholders
Second half of 2025
- Enbridge decides to proceed with optimization work
- Regulatory permit applications begin to be filed
2026
- Ongoing permit applications filed where required
- Construction at Enbridge facilities expected to begin, pending receipt of required regulatory approval
2027
- Construction continues
2028
- Mainline Optimization Phase 1 goes into service
Mainline Optimization Phase 2 (preliminary timeline)
First half of 2026
- Public engagement begins with adjacent landowners, government, Tribal Nations, First Nations and Métis governments, as well as other interested stakeholders
Mid-2026
- Enbridge makes a decision on whether this project proceeds
Second half of 2026
- Required regulatory applications begin to be filed (pending a decision to proceed with the project)
2027 and 2028
- Ongoing permit applications filed where required
- Construction at Enbridge facilities expected to begin
- Targeted project in-service date late 2028