Mainline Optimization

Return to project

Program timelines

Mainline Optimization Phase 1

2024

  • Early project planning and development

First half of 2025

  • Ongoing project design and development
  • Public engagement begins with government, Tribal Nations, First Nations and Metis governments, as well as other interested stakeholders

Second half of 2025

  • Enbridge decides to proceed with optimization work
  • Regulatory permit applications begin to be filed

2026

  • Ongoing permit applications filed where required
  • Construction at Enbridge facilities expected to begin, pending receipt of required regulatory approval

2027

  • Construction continues

2028

  • Mainline Optimization Phase 1 goes into service

Mainline Optimization Phase 2 (preliminary timeline)

First half of 2026

  • Public engagement begins with adjacent landowners, government, Tribal Nations, First Nations and Métis governments, as well as other interested stakeholders

Mid-2026

  • Enbridge makes a decision on whether this project proceeds

Second half of 2026

  • Required regulatory applications begin to be filed (pending a decision to proceed with the project)

2027 and 2028

  • Ongoing permit applications filed where required
  • Construction at Enbridge facilities expected to begin
  • Targeted project in-service date late 2028