Ridgeline Expansion Project
Return to projectProject Timeline
TVA
June 2021
- TVA files Notice of Intent
- TVA public scoping meeting
Summer/Fall 2022
- TVA draft Environmental Impact Statement
- TVA public comment period
Spring/Summer 2023
- TVA final Environmental Impact Statement
- TVA Record of Decision
Enbridge
Fall 2021:
- Enbridge held landowner open houses
Spring/Summer 2022
- Enbridge begins FERC pre-filing process
- Enbridge holds community open houses
Spring/Summer 2023
- Enbridge begins FERC application process (depending on TVA decision)
- FERC public comment period
Fall 2025
- Oct. 2: Received FERC Notice to Proceed
- Oct. 21: Construction begins
- Nov. 1: Clearing begins from project’s east side
- Dec. 1: Clearing begins from project’s west side
November 2026
- Project in service
Spring 2027
- Cleanup and restoration complete