Rio Bravo Pipeline Project

Return to project

Project Updates

  • September 2019: NextDecade and Enbridge Announce Strategic MOU for the Development of Rio Bravo Pipeline for the Rio Grande LNG Project. Read the release.
  • November 2019: FERC approves the Rio Bravo Pipeline Project under Docket No. CP16-455-000.
  • March 2020: NextDecade and Enbridge Sign Definitive Agreement Regarding Rio Bravo Pipeline whereby Enbridge acquires and assumes all responsibilities for the development, construction and operation of the pipeline. Read the release.
  • June 2020: Amendment to the certificate of public convenience and necessity filed under Docket No. CP20-481-000.
  • April 2023: FERC approves amendment to the certificate under Docket No. CP20-481-000.
  • July 2023: Second amendment to the certificate filed under Docket No. CP23-519-000.

On July 20, 2023, Rio Bravo submitted a second amendment to the application to adjust the pipeline route to align the FERC-approved route with other permits and other federal guidance. The adjusted route will minimize impacts to potential ocelot habitat, address U.S. Fish and Wildlife Service concerns regarding impacts on this habitat and species, address agency and landowner concerns, avoid recently constructed infrastructure, increase constructability, enhance safety of construction and operations, affect fewer wetlands, forest lands, and prime farmland soils, and align the Rio Bravo Pipeline Project with the updated design of the LNG Terminal to which it will interconnect.