Leaf River Wind Project
Return to projectProject Updates
- Project layout and site review activities expected to be completed by July 20, 2026
- Special Use Permit (SUP) application to be submitted to the County in September 2026
- Construction anticipated to begin in 2028
- Leaf River Wind expected to be fully operational by September 2029